Nkandla: Documents call Zuma's bluff |
Publication |
Mail & Guardian |
Date | 2012-11-23 |
Reporter |
Sally Evans, Lionel Faull, Phillip de Wet |
Web link | www.mg.co.za |
Between
2010 and 2012, Jacob Zuma's share of the cost of
developments was halved, while the government's
bill doubled
(Rogan Ward, M&G)
An M&G investigation reveals that President
Jacob Zuma was kept up to date about
developments and
taxpayer money was used for his private
homes.
President Jacob Zuma was provided with
exhaustive details
about progress on the security project at his
Nkandla complex in November 2010, documents
provided to the M&G Centre for
Investigative Journalism on Thursday show. They
cast doubt on his vehement denial in Parliament
last week that he was unaware of the scale of
construction.
The documents, which refer euphemistically to
the Nkandla expansion as "prestige project A",
reveal how Zuma's supposed private contribution
dwindled by half
from more than R20-million to slightly more than
R10-million, while the
total costs more than doubled.
They also show that taxpayer money was also
spent on buildings for the personal use of the
Zuma family and not only for new, adjoining
security infrastructure, as claimed by the
department of public works when first confronted
about the R250-million spent on Nkandla.
Also clear from the documents are the large
contributions expected from the department of
public works for the completion of buildings
that Zuma told Parliament were entirely paid for
by his family, particularly a new guest
residence and two new private residences.
The documents also show that at least one
minister became involved in the nitty-gritty of
construction at the site after delays mounted.
Although the Mail & Guardian has been
unable to verify all the documents
independently, some of which are marked "top
secret", the timing and some of the details
corroborate information previously provided by a
highly placed source.
Overseeing the work
Perhaps the most damning of the documents is
a letter addressed to Zuma in which the then
newly appointed
public works minister, Gwen
Mahlangu-Nkabinde, writes: "I have taken the
view that it is prudent to update you on the
progress of the above prestige project", before
giving precise expected completion dates for 17
individual components of construction. The
letter contains an even more detailed progress
report from the project managers responsible for
overseeing the work.
Last week Zuma told Parliament he was not aware
of the cost of the security installation at
Nkandla.
"What the government did, given its own
considerations of security, was to build other
houses beyond my home for the security
personnel," he said during an off-the-cuff
answer to questions. "These are not shown on
television and these are really the government's
houses, but I do not know how much they cost …
Now, I do not know where this amount of money
went to."
His answer to Parliament focused on three
elements of the security upgrade: fencing,
bulletproof windows and an underground bunker.
But the documents show that he was also kept
abreast of progress on a tuck shop, a sewerage
treatment plant, the upgrading of water supplies
and other elements.
Although the letter to Zuma does not include
information about the costs involved, minutes of
meetings and internal memos from the department
of public works make it seem likely that the
amounts would have been brought to his
attention.
Bullet-resistant glass
Mahlangu-Nkabinde was not the only minister
deeply involved in the project. In September
2010, her
predecessor, Geoff Doidge, appears to
have become involved in frantic attempts to
fast-track the construction. In minutes of an
emergency meeting held at the Nkandla site,
Doidge complains about delays in the provision
of bullet-resistant glass and the short time
remaining for the completion of the interior
design.
Changing the public works minister in mid-stride
did not prevent high-level continuity of the
project – director general Siviwe Dongwana
attended both the site meeting with Doidge and
later prepared at least one memo to brief
Mahlangu-Nkabinde on the issue.
If Zuma's statement that he was ignorant of the
costs is accepted, it would imply that neither
Doidge nor Mahlangu-Nkabinde considered it worth
mentioning that, at the time, the estimated
project cost had already exceeded R100-million.
A memo also shows that an internal security
director in the presidency was involved in the
original scoping of the security work, further
expanding the pool of people who had access to
Zuma and, possibly, a duty to inform him of the
cost implications.
Although instructions from the president are
never mentioned, a nervousness about the delays
– which also delayed building work being done by
Zuma's contractors – is evident. "On or about
the end of June 2010, it became evident that
some of the major activities related to the
security installation had not progressed to the
extent as was originally envisaged," one public
works memo states.
Among the sticking points were that a specialist
security consultant had not yet been appointed
for the work, 10 months after the project was
initiated. Such delays would eventually see
Doidge, and others, including
surgeon general
Veejay Ramlakan, become personally
involved in window-frame lead times, expediting
the delivery of sections of fencing and
establishing how
much water would be required for the
festive season.
Large contributions
From the leaked documents available and the
financial details in the latest documents, it
seems that the total cost of construction
escalated from R111.3-million in the later part
of 2010 to R248-million during 2012.
The documents show that the department of public
works was expected to make large contributions
for the completion of three residences that Zuma
told Parliament were entirely paid for by his
family.
These residences were expected to cost
R19.4-million, of which the department was going
to pay R6.5-million. It would also pay for the
bulk of the earthworks and stormwater drains
around the new residences.
As of late 2010, Zuma was expected to pay a
total of R22.6-million towards the improvements.
But in the face of the steadily escalating costs
of the project, Zuma's overall contribution
appears to have been revised down to
R10.6-million.
Shortly before the Mail & Guardian went
to print, presidential spokesperson Mac Maharaj
referred all questions to public works.
The two previous public works ministers could
not be reached for comment.
Our Coverage
More Coverage
Read more…
Sally Evans and Lionel Faull work for the M&G
Centre for Investigative Journalism (amaBhungane)
With acknowledgement to Sally Evans, Lionel Faull, Phillip de Wet and Mail & Guardian.
Instead of this
low-life having another 13 years to serve in
Westville Prison, the criminals in the NPA let
him and joined-at-the-hip benefactor Thomson-CSF
free to allow them to escalate their ZAR500 k
racketeering business into a full blown
multi-billion Rand grand larceny against the
nation.
I must now stop, my bucket runneth over.